Carrig

Location: Carrig, Nr.Ballinagarry, Co. Tipperary

Client: Econnect Construction Ltd.(UK)

Work Scope: 
Construct 1 no. 20kv Substation building at the 2.55MW Carrig Wind Farm in north Co. Tipperary. The substation was included in the civils package awarded to Wind Farm Civils which also included the construction of 3 no. Vestas V52 turbine foundation. The work was carried out in spring 2006.